Print Options

Card layout: ?

← Back to notecard set|Easy Notecards home page

Instructions for Side by Side Printing
  1. Print the notecards
  2. Fold each page in half along the solid vertical line
  3. Cut out the notecards by cutting along each horizontal dotted line
  4. Optional: Glue, tape or staple the ends of each notecard together
  1. Verify Front of pages is selected for Viewing and print the front of the notecards
  2. Select Back of pages for Viewing and print the back of the notecards
    NOTE: Since the back of the pages are printed in reverse order (last page is printed first), keep the pages in the same order as they were after Step 1. Also, be sure to feed the pages in the same direction as you did in Step 1.
  3. Cut out the notecards by cutting along each horizontal and vertical dotted line
To print: Ctrl+PPrint as a list

158 notecards = 40 pages (4 cards per page)

Viewing:

1 Exam Prep Florida Building Code – Residential, 2017 Questions and Answers

front 1

One- and two-family dwellings shall have which of the following characteristics?

back 1

  • Be not more than three stories above grade plane in height
  • have a separate means of egress

front 2

All emergency escape and recue openings shall have a minimum net clear opening height of _________ inches.

back 2

24

front 3

What is the minimum required depth for the firebox of a concrete or masonry fireplace?

back 3

20 inches

front 4

What is the minimum required clearance between combustible materials and the outside surface of a masonry heater?

back 4

36 inches

front 5

Any factory-built chimney used for a medium-heat appliance that produces flue gases with a temperature in excess of ____°F is required to comply with UL 959.

back 5

1,000

front 6

What is the minimum required clearance between combustibles and all parts of a duct within 5 feet of the duct outlet?

back 6

1-inch

front 7

The total required width of the enclosing space for a furnace or air handler is required to be _____ inches
wider than the furnace or air handler.

back 7

12

front 8

Table M1306.2 ______ be used to reduce the clearance required for solid-fuel appliances listed for installation with minimum clearances of 12 inches or less.

back 8

May not

front 9

If piping is to be concealed and is installed through notches in studs of less than 1.5 inches from the nearest edge of the member, the pipe shall __________________.

back 9

  • Be protected by shield plates having a minimum thickness of 0.0575-inch No. 16 gage
  • Cover the area of the pipe where the member is notched or bored
  • Extend a minimum of 4 inches above sole plates and below top plates

front 10

A minimum of ______ inches in front of combustion air openings shall remain unobstructed.

back 10

6

front 11

Electric heat pumps shall ________________.

back 11

Listed and labeled in accordance with UL1995

front 12

What is the maximum allowable operating temperature for a radiant heating system operating on a gypsum assembly?

back 12

125°F

front 13

A duct heater may only be installed within 4 feet of a heat pump or air conditioner if it is listed and labeled for such installations.

back 13

True

front 14

Location of floor furnaces shall conform to which of the following requirements?

back 14

  • Floor registers of floor furnaces shall be installed not less than 6 inches from a wall
  • Wall registers of floor furnaces shall be installed not less than 6 inches from the adjoining wall at inside corners

front 15

The door swing radius is prohibited to exceed _____ inches from the furnace air inlet or outlet when measured at right angles to the opening.

back 15

12

front 16

Room heaters shall be installed on _________.

back 16

Approved assemblies constructed of noncombustible materials that extend at least 18 inches beyond the
appliance on all sides and noncombustible floors

front 17

Where a cooling coil is located in the supply plenum of a warm-air furnace, the furnace blower shall be
rated at a minimum of __-inch water column static pressure.

back 17

0.5

front 18

Evaporative coolers are required to be installed ______________.

back 18

on a level platform

front 19

The air removed from bathrooms by mechanical exhaust system shall be discharged to which of the
following?

back 19

the outdoors

front 20

Exhaust ducts shall be supported at intervals not to exceed _____?

back 20

12 feet

front 21

A single-wall duct that serves a range hood shall be constructed of ______.

back 21

  • galvanized steel
  • stainless steel
  • copper

front 22

Use of a domestic open-top broiler unit requires a metal exhaust hood with which of the following
characteristics?

back 22

  • a minimum thickness of 0.0157-inch, No. 28 gage
  • 1/4 inch clearance between the hood and the underside of combustible material or cabinets

front 23

Underground duct systems shall be constructed of which of the following?

back 23

  • approved concrete
  • clay
  • metal

front 24

The screens required to cover outdoor air inlets shall have openings that are a minimum of 1/4 inch and a maximum of ______ inch.

back 24

1/2

front 25

A solid-fuel-burning appliance will require which of the following?

back 25

combustion air

front 26

All emergency escape and recue openings shall have a minimum net clear opening of _________ square feet.

back 26

5.7

front 27

Any pressure difference between the air at the regulator and the combustion air supply is to be avoided by the use of draft regulators.

back 27

True

front 28

A flue collar for an appliance is required to be ________ than the connector.

back 28

larger

front 29

Any vent for a natural draft appliance shall terminate a minimum of _____ feet above the highest connected appliance outlet.

back 29

5

front 30

A chimney connector is required to enter a masonry chimney a minimum of ______ inches above the
bottom of the chimney.

back 30

6

front 31

What is the minimum vertical clearance required above the cook top of a freestanding or built-in range?

back 31

30 inches

front 32

The thermostat for a sauna heater is required to limit the room temperature to a maximum of ______°F.

back 32

194°F

front 33

The lowest piping that collects the discharge from all other drainage piping inside the house and extends 30 inches beyond the exterior walls is

back 33

building drain

front 34

A minimum vertical developed length of _____ feet, between a horizontal branch and a drainage stack is a branch interval.

back 34

8

front 35

Continuous waste is defined as a drain from two or more similar adjacent fixtures connected to _______ trap.

back 35

a single

front 36

A continuous passageway for the transmission of air is __________.

back 36

a duct system

front 37

Air, passing through the combustion chamber and the appliance flue, that exceeds what is theoretically
required for complete combustion, is excess air.

back 37

True

front 38

A foam plastic insulation will generally have a maximum density of ______ pounds per cubic foot.

back 38

20

front 39

A masonry heater is a solid fuel burning heating appliance that mainly consists of concrete or solid masonry having a mass of at least 1,100 pounds, ______ the chimney and foundation.

back 39

excluding

front 40

A shutoff valve __________ required in a system with a single low-pressure steam boiler.

back 40

is not

front 41

Boiler discharge shall be piped, by gravity, to _____.

back 41

  • within 18 inches of the floor
  • an open receptor

front 42

Expansion tanks are required for hot water boilers.

back 42

True

front 43

Storage closets are ______ for the operation of fuel- fired water heaters.

back 43

prohibited

front 44

Hydronic piping shall be hydrostatically tested using a minimum pressure of ______ pounds per square
inch for a duration of not less than 15 minutes and not more than 20 minutes.

back 44

100

front 45

Piping embedded in concrete or gypsum materials, shall be _________ with a minimum rating of 100 psi at 180°F.

back 45

A. standard-weight steel pipe
B. chlorinated polyvinyl chloride
C. polypropylene

front 46

Solder joints in a metal pipe are prohibited anywhere within ________ inches of a transition from such metal pipe to PE-RT pipe.

back 46

18

front 47

The assembled loop system shall be pressure tested with water at _____ psi for 15 minutes with no observed leaks before connection trenches are backfilled.

back 47

100

front 48

What is the maximum amount of fuel oil allowed in above ground storage or inside of a building?

back 48

660

front 49

Where window emergency escape and rescue openings are provided, they shall have a sill height of not more than _____________ above the floor.

back 49

44

front 50

Fill piping will be required to terminate a minimum of ______ feet outside of a building opening at the same or lower level.

back 50

2

front 51

What is the maximum allowable pressure at the oil supply inlet to an appliance?

back 51

3 pounds per square inch

front 52

Which of the following is governed by Chapter 24 of the Florida Building Code 2010, Residential.

back 52

  • fuel-gas piping systems
  • fuel-gas appliances
  • combustion air configuration

front 53

53. An auxiliary drain pan ________ required for any appliance that automatically shuts down operation in the event of a stoppage in the condensate drainage system.

back 53

shall not be

front 54

Which of the following appliances shall not be located in a sleeping room?

back 54

None of the above

front 55

____________ require combustion, ventilation and dilution air.

back 55

  • Direct-vent appliances
  • Gas appliances
  • Natural draft design and vented gas appliances

front 56

The source of ignition for equipment and appliances so equipped is required to be a minimum of _________ inches above the floor in hazardous locations.

back 56

18

front 57

Which of the following methods is required for the flashing for a vertical sidewall?

back 57

  • step-flashing
  • continuous "L"

front 58

Gas piping will be considered to be bonded where it is connected to an appliance that is connected to the equipment grounding conductor of the circuit supplying that appliance.

back 58

True

front 59

Exposed piping, other than steel pipe, shall be identified by a yellow label marked "Gas", in black letters, and spaced at maximum intervals of ______ feet.

back 59

5

front 60

What is the maximum design operating pressure for piping systems located inside buildings?

back 60

5 pounds per square inch gauge

front 61

Anodeless risers shall be ___________.

back 61

  • factory-assembled
    recommended by the manufacturer
    leak-tested by the manufacturer

front 62

Piping systems, installed underground, are required to be a minimum of ____ inches below grade.

back 62

12

front 63

The radius of the inner curve of plastic pipe bends for gas piping shall be a minimum of ______ times the inside diameter of the pipe.

back 63

25

front 64

When pressure testing piping systems, the test duration shall be a minimum of ______ minutes.

back 64

10

front 65

To prevent traps, piping for other than dry gas conditions shall be sloped a minimum of 0.25 inch in ____ feet.

back 65

15

front 66

Anytime an appliance shutoff valve is installed at a manifold, it shall be located within ______ feet of the
appliance served.

back 66

50

front 67

A pressure regulator that requires a vent shall be vented directly _________.

back 67

to the outdoors

front 68

What is the maximum allowable length for connectors, for gas appiances?

back 68

6

front 69

The connectors for a masonry chimney shall connect a minimum of ______ inches above the lowest portion of the interior of the chimney flue.

back 69

12

front 70

What is the minimum required thickness for an insulation shield?

back 70

26 gage

front 71

Venting systems are prohibited from passing through which of the following?

back 71

  • fabricated air duct
  • furnace plenum

front 72

The maximum common vent capacity listed in the venting tables are required to be reduced by _____ percent for each elbow up to and including 45 degrees in the common vent.

back 72

5

front 73

Ducts are _________ attached to wall furnaces.

back 73

prohibited from being

front 74

The lowest portion of the floor furnace shall have a minimum of a ______-inch clearance from the grade
level.

back 74

6

front 75

What is the minimum required support interval for domestic clothes dryer exhaust ducts?

back 75

4 ft

front 76

Any warning on a sauna heater notice shall ________________.

back 76

  • be easily readable
  • contrast with its background
  • have wording a minimum of 0.25 inch high

front 77

For a forced-air warm-air furnace, the minimum unobstructed total area of the outside and return air ducts or openings shall be ______ square inches for each 1,000 Btu/h output rating capacity of the furnace.

back 77

2

front 78

What is the minimum required clearance to combustible materials at the side for a suspended-type unit heaters?

back 78

18 inches

front 79

79. What is the maximum Btu/h per cubic foot of volume allowed for all unvented appliances installed in a room or space?

back 79

20

front 80

The cook top of a household cooking appliance is required to have a vertical clearance of at least 30 inches to ___________.

back 80

  • combustible materials
  • metal cabinets

front 81

81. If an appliance pressure regulator is not supplied with an illuminating appliance and the service line is notbequipped with a service regulator, an appliance pressure regulator ______ installed in the line to the
illuminating appliance.

back 81

shall be

front 82

An infrared radiant heater shall be fixed in a position separate from _______ supply lines.

back 82

  • gas
  • electric

front 83

Class _____ roofing shall be installed in areas designated by law as requiring their use or when the edge of the roof is less than 3 feet from a property line.

back 83

  • A
  • B
  • C

front 84

In concealed locations, where piping other than ____________, is installed through holes or notches in
studs, joists, rafters or similar members less than 1 1/4 inches from the nearest edge of the member, the pipe shall be protected by steel shield plates.

back 84

Cast-iron or galvanized steel

front 85

Footings ______ extend below the 45-degree bearing plane of the bottom edge of a wall or footing when trenching is installed parallel to the footings.

back 85

shall not

front 86

What is the minimum diameter for fixture tail pieces for sinks, dishwashers, laundry tubs, bathtubs and similar fixtures?

back 86

1 1/2 inches

front 87

What is the minimum utility space required for fixtures with concealed slip-joint connections?

back 87

12 inches

front 88

Standpipes shall extend not greater than _____ inches above the trap weir?

back 88

42 inches

front 89

What is the minimum required interior cross sectional area for a shower compartment? (Excluding exceptions)

back 89

900 square inches

front 90

Shower receptors are required to have a finished curb threshold a minimum of ______ inch below the sides and back of the receptor.

back 90

1

front 91

What is the maximum temperature a water temperature- limiting device?

back 91

120°F

front 92

What is the minimum required diameter of sink waste outlets?

back 92

1 1/2

front 93

Which of the following is required for floor drains with waste outlets?

back 93

  • shall be a minimum of 2 inches in diameter
  • shall have a removable strainer

front 94

What is the minimum required weight for sheet copper used for flush tank linings?

back 94

10 ounces per square foot

front 95

A pan drain shall ________________.

back 95

  • extend full-size and terminate over a suitably located indirect waste receptor
  • extend to the exterior of the building

front 96

Where heated water is discharges from a solar thermal system to a hot water distribution system, a
thermostatic mixing valve is required to be installed to temper the water to a temperature not exceeding
______°F.

back 96

140

front 97

A temperature relief valve is required to be installed to allow the temperature-sensing element to monitor the water within the top ____ inches of the tank.

back 97

6

front 98

Flush tanks are required to be equipped with an anti-siphon fill valve backflow preventer installed a
minimum of ____ inch(es) above the full opening of the overflow pipe.

back 98

1

front 99

What is the maximum static pressure for a water supply system?

back 99

80 psi

front 100

Protection from exposure in the form of ____________ is required for nonmetallic pipe and tubing systems.

back 100

  • 3/8 inch thick gypsum wallboard
  • 1/2 inch thick plywood
  • material having a 15 minute fire rating

front 101

Solders and fluxes used for joints in potable water- supply systems shall be required to have a maximum of ___ percent lead.

back 101

0.2

front 102

Buildings and structures, including all related parts, are required to be constructed to safely support which of the following?

back 102

  • live/dead loads
  • roof/wind loads
  • flood/snow loads

front 103

If a roof surface adjacent to a wall or walls is at the same elevation, the parapet shall extend a minimum of ______ inches above the roof surfaces.

back 103

30

front 104

Mechanical and gravity outdoor air intake openings shall be located at least ______ feet from any hazardous or noxious contaminant. such as vents, chimneys, plumbing vents, streets, alleys, parking lots and loading docks, except as otherwise specified in this code.

back 104

10

front 105

What shall not be considered as contributing to the minimum required habitable area for a room?

back 105

  • portions of a room with a sloping ceiling measuring less than 5 feet
  • a furred ceiling measuring less than 7 feet from the finished floor to the finished ceiling

front 106

A basement that does not include habitable space, hallways, bathrooms, toilet rooms and laundry rooms is required to have a minimum ceiling height of ______.

back 106

6 feet 8 inches

front 107

Sloped glazing is defined as glass or other transparent or translucent glazing material installed at a minimum slope of ______ degrees from vertical.

back 107

15

front 108

Emergency and escape rescue openings shall have a net clear opening of not less than ______ square feet.

back 108

5.7

front 109

What is the minimum required headroom, in all parts of a stairway, measured vertically from the sloped line adjoining the tread nosing or from the floor surface of the landing or platform on that portion of the stairway? on that portion of the stairway.

back 109

6 feet 8 inches

front 110

Required guards shall be located along open-sided walking surfaces, including stairs, ramps and landings, if they are located more than ______ inches measured vertically to the floor or grade below at any point within 36 inches horizontally to the edge of the open side.

back 110

30

front 111

Foam plastics __________ permitted as interior finish.

back 111

shall be

front 112

The quality mark, required on each piece of pressure- preservative-treated lumber or plywood, shall include ____________.

back 112

identification of treating plant

front 113

An area that is considered to be subject to wave heights in excess of ______ feet or subject to high-
velocity wave action or wave-induced erosion shall be designated as coastal high-hazard areas.

back 113

3

front 114

Water service pipe shall be installed _______.

back 114

  • a minimum of 12 inches deep
  • less than 6 inches below the frost line

front 115

What is the minimum required weight for sheet copper for general use?

back 115

12 ounces per square feet

front 116

Joints for hub and spigot pipe are required to be ________.

back 116

  • be firmly packed with oakum or hemp
  • have molten lead poured in one operation to a minimum depth of 1 inch

front 117

Cleanouts shall be installed a maximum of ______ feet apart in horizontal drainage lines when measured from the upstream entrance of the cleanout.

back 117

100

front 118

_______ that receive the discharge of water closets shall be capable of handling spherical solids with a
diameter of up to and including 2 inches.

back 118

  • Pumps
  • Ejectors

front 119

Plumbing systems, with a system of vent piping permitting the admission or emission of air that allows the seal of any fixture trap is required to be subjected to a pneumatic pressure differential of more than _____ inch(es) of water column.

back 119

1

front 120

Open vent pipes that extend through a roof shall be terminated a minimum of __________, whichever is
greater.

back 120

  • 6 inches above the roof
  • 6 inches above the anticipated snow accumulation

front 121

Every dry vent shall rise vertically to at least _____ inches above the flood level rim of the highest trap or trapped fixture being vented.

back 121

6

front 122

A vent will be required to be installed at least ______ pipe diameters away from the trap weir.

back 122

two

front 123

A single horizontal wet vent may be used to vent any combination of fixtures within two bathroom groups and located on the same floor level.

back 123

True

front 124

A waste stack ______ used as a vent for all of the fixtures discharging to the stack.

back 124

may be

front 125

What is the maximum allowable slope of the vent section of a horizontal branch drain?

back 125

8-percent slope

front 126

If the size of the trap is 1 1⁄4 inches and the slope is 1⁄4 inches per foot, the maximum distance of the fixture trap from the vent must be ____________ feet.

back 126

5

front 127

A vent or branch vent for multiple island fixture vent should extend at least ______ inches above the highest island fixture being vented.

back 127

6

front 128

What is the maximum diameter for a vent pipe?

back 128

1 1/4

front 129

If an air admittance valve is installed in an attic, it shall be installed at least ______ inches above insulation materials.

back 129

6

front 130

Traps will be required to have a liquid seal of __________.

back 130

  • not less than 2 inches
  • not more than 4 inches

front 131

A subsoil drain shall be a minimum of ______ inches in diameter.

back 131

4

front 132

A sump pit shall be a minimum of 18 inches in diameter and ______ inches deep, unless otherwise
approved.

back 132

24

front 133

Lots shall be graded, to fall a minimum of 6 inches within the first ______ feet, to drain surface water
away from foundation walls.

back 133

10

front 134

A fastener that is used below grade to attach plywood to the exterior side of exterior basement wall studs shall be of Type ______ stainless steel.

back 134

  • 304
  • 316

front 135

What is the minimum required thickness for spread footings?

back 135

8 inches

front 136

Concrete and masonry foundation walls will be required to extend a minimum of __ inches above the finished grade adjacent to the foundation for a masonry veneer.

back 136

4

front 137

What is the minimum thickness of portland cement parging required to be applied to the exterior of a
masonry foundation wall for dampproofing?

back 137

3/8 inch

front 138

What is the minimum required nominal size for structural wood columns?

back 138

4 x 4

front 139

Mechanical exhaust ventilation operating continuously at a rate equal to ______ cubic foot per minute for each 50 square feet of crawlspace floor area, including an air pathway to the common area, and perimeter walls, shall not require ventilation openings.

back 139

1

front 140

Hair and lint strainers are required in the pool circulating pumps when used with a pressure filter.

back 140

True

front 141

Structural glue-laminated members are prohibited, without exception.

back 141

False

front 142

______ shall be pressure preservative treated and dried after treatment.

back 142

  • Sleepers
  • Joists
  • Plywood subflooring

front 143

Concrete slab-on-ground floors shall be at least ______ inches thick.

back 143

3.5

front 144

Which of the following shall not extend beneath walls, partitions or columns which are fastened to the floor?

back 144

  • a compressible floor-covering that compresses more than 1/32 inch when subjected to 50 pounds applied over 1 inch square of material
  • compressible floor-coverings that are greater than 1/8 inch in thickness in the uncompressed state

front 145

Mortar joint thickness for a load-bearing masonry wall shall be the same for which of the following?

back 145

head joints and collar joints

front 146

When bonding with wall ties, there shall be at least one metal tie for each ______ square feet of wall area.

back 146

4.5

front 147

The maximum spacing of reinforcement shall be inches provided that the walls are solid
grouted and constructed of hollow open-end units, hollow units laid with full head joints or two wythes of solid units.

back 147

48

front 148

If design wind pressure is ______ psf, the maximum area of each individual standard-unit glass panel shall be 144 square feet.

back 148

20

front 149

A construction joints, in a plain concrete wall, including a wall that is required to have a minimum of No.4 bars at _____ inches on center, shall be located at points of lateral support.

back 149

48

front 150

The bottom surface of footings shall not have a slope exceeding one unit vertical in units horizontal.

back 150

10

front 151

What is the maximum side dimension, centered in the panel core, for the maximum vertical chase
penetration in SIPs?

back 151

2 inches

front 152

Exterior sheathing shall be _______ before applying an exterior cover.

back 152

dry

front 153

The finish coat for two-coat cement plaster shall not be applied sooner than ______ hours after application of the first coat.

back 153

48

front 154

What is the maximum nominal air space allowed between a masonry veneer and the sheathing?

back 154

4 1/2

front 155

Anytime expansive or collapsible soils are known to exist, dwellings are required to have a means of
discharging water from a roof to a minimum of _______ feet away from the foundation walls.

back 155

5

front 156

Wood structural panel used as roof sheathing shall be installed with joints ____________.

back 156

staggard

front 157

Insulation shall not block the free flow of air when eave or cornice vents are installed and a minimum of a ______-inch space is required between the insulation and the roof sheathing and at the location of the vent.

back 157

1

front 158

If a building is constructed with a combustible ceiling or roof, what is the required maximum attic access opening to attic areas?

back 158

30 square feet