front 1 Project charter is an input to all of the following processes EXCEPT: a) Collect requirements | back 1 b) Create WBS |
front 2 The CCB approved a major scope change to a project, aware that it will increase costs and delay delivery. Which of the following is true? a) Project baselines should be updated to reflect this | back 2 a) Project baselines should be updated to reflect this |
front 3 The WBS dictionary contains an entry for every: a) Work package | back 3 a) Work package |
front 4 The scope baseline is output by what process? a) Plan scope management | back 4 c) Create WBS |
front 5 The validate scope process receives ______ deliverables and outputs _______ deliverables. a) Completed; validated | back 5 c) Verified; accepted |
front 6 The work on your project has generally finished and you want to commence a solid closing process for the project. What should have happened before beginning this process? a) Lessons learned have been placed into a repository | back 6 d) Deliverables of the project have been accepted |
front 7 To gather more detailed requirements for a claims data entry system, Joe sits down with a claims clerk to perform the process to create a claim himself. Joe is using what interpersonal technique? a) Storyboarding | back 7 d) Participant observer |
front 8 Which of the following is not an output of the control scope process? a) Accepted deliverables | back 8 a) Accepted deliverables |
front 9 Which of the following is not found in the scope baseline? a) Requirements Documentation | back 9 a) Requirements Documentation |
front 10 Which should be included in a requirements management plan? a) Description of processes to be used to validate
deliverables | back 10 c) Description of processes to be used to gather, document, and manage requirements |