A recent weakness in an enemy's defensive capabilities has been detected. As a result, your project, which exploits this weakness, has suddenly been given a higher priority. Resources from other projects will be turned over to your project to move the delivery time to an earlier date than originally estimated. This strategy is best characterized as what?
a) Fast tracking
b) Crashing
c) Sheer craziness
d)
Resource leveling
b) Crashing
A schedule activity may begin 10 days before its predecessor activity finishes. This is an example of:
a) Dependency determination and integration
b) Precedence
diagramming method (PDM)
c) Dependency with a lead
d)
Dependency with a lag
c) Dependency with a lead
A schedule network diagram shows:
a) Dependencies among activities
b) Dependencies among
activities and activity start and finish dates
c) Dependencies
among activities and activity durations
d) Activity durations and
start dates
a) Dependencies among activities
An important part must be completed before an oil rig construction project can finish. The optimistic time estimate for completing this part is 4 days, the pessimistic estimate is 19 days, and the most likely estimate is 7 days. You view these estimates to have a triangular distribution, so the expected duration is:
a) 10.0 days
b) 8.5 days
c) 6.5 days
d) 7.5 days
a) 10.0 days
An important part must be completed before an oil rig construction project can finish. The optimistic time estimate for completing this part is 4 days, the pessimistic estimate is 19 days, and the most likely estimate is 7 days. Assuming the most likely estimate is truly most likely, what is the expected duration?
a) 7.5 days
b) 8.5 days
c) 6.5 days
d) 10.0 days
b) 8.5 days
Analogous duration estimating is:
a) Frequently used to estimate project duration when there is a
limited amount of detailed information about the project
b)
Similar to multiple duration estimating
c) The same as bottom-up
estimating
d) Generally more accurate than other duration
estimating methods when expert judgment is used
a) Frequently used to estimate project duration when there is a limited amount of detailed information about the project
If your expected duration is 110 days and the standard deviation is 12, which of the following is true?
a) There is approximately a 68% chance of completing this activity
in 98 to 122 days
b) There is approximately a 99% chance of
completing this activity in 86 to 134 days
c) There is
approximately a 75% chance of completing this activity in 86 to 134
days
d) There is approximately a 95% chance of completing this
activity in 98 to 122 days
a) There is approximately a 68% chance of completing this activity in 98 to 122 days
Knowledge of best practices in a particular area is most likely to give rise to which type of dependency?
a) External
b) Mandatory
c) Soft logic
d) Finish-to-Start
c) Soft logic
The amount of time an activity can be delayed without delaying the entire project is known as what?
a) Total float
b) Critical path
c) Zero float
d)
Free float
a) Total float
The schedule management processes include:
a) Define activities; Sequence activities; Estimate activity
durations; Develop schedule; Control schedule
b) Identify
activities; Develop schedule; Execute activities; Control activities;
Monitor schedule
c) Define activities; Sequence activities;
Execute activities; Estimate activity durations; Control
schedule
d) Determine activities; Sequence activities; Estimate
activity durations; Develop schedule; Monitor schedule
a) Define activities; Sequence activities; Estimate activity durations; Develop schedule; Control schedule
Which of the following statements is true of the resource optimization techniques?
a) Resource optimization techniques are used in the processes
Estimate activity durations, Develop schedule, and Control
schedule
b) Resource leveling changes start and finish dates of
activities, but resource smoothing does not
c) Resource smoothing
cannot change the critical path
d) Resource optimization
techniques include crashing and fast-tracking
c) Resource smoothing cannot change the critical path