Project charter is an input to all of the following processes EXCEPT:
a) Collect requirements
b) Create WBS
c) Define
Scope
d) Develop project management plan
b) Create WBS
The CCB approved a major scope change to a project, aware that it will increase costs and delay delivery. Which of the following is true?
a) Project baselines should be updated to reflect this
b)
There are several reasons to change a baseline, but scope changes are
not one of them
c) The scope baseline should be updated, but not
the other baselines
d) Project baselines should never be updated
a) Project baselines should be updated to reflect this
The WBS dictionary contains an entry for every:
a) Work package
b) Requirement
c) Major
deliverable
d) Project phase
a) Work package
The scope baseline is output by what process?
a) Plan scope management
b) Create scope baseline
c)
Create WBS
d) Define scope
c) Create WBS
The validate scope process receives ______ deliverables and outputs _______ deliverables.
a) Completed; validated
b) Validated; verified
c)
Verified; accepted
d) Verified; validated
c) Verified; accepted
The work on your project has generally finished and you want to commence a solid closing process for the project. What should have happened before beginning this process?
a) Lessons learned have been placed into a repository
b) Final
product, service, or result transition has been finished
c)
Updates to organizational process assets have been completed
d)
Deliverables of the project have been accepted
d) Deliverables of the project have been accepted
To gather more detailed requirements for a claims data entry system, Joe sits down with a claims clerk to perform the process to create a claim himself. Joe is using what interpersonal technique?
a) Storyboarding
b) Joint application design
c) Job
shadowing
d) Participant observer
d) Participant observer
Which of the following is not an output of the control scope process?
a) Accepted deliverables
b) Work performance
information
c) Project document updates
d) Change requests
a) Accepted deliverables
Which of the following is not found in the scope baseline?
a) Requirements Documentation
b) WBS
c) WBS
Dictionary
d) Scope Statement
a) Requirements Documentation
Which should be included in a requirements management plan?
a) Description of processes to be used to validate
deliverables
b) The requirements documentation
c)
Description of processes to be used to gather, document, and manage
requirements
d) The requirements traceability matrix
c) Description of processes to be used to gather, document, and manage requirements